₱97.9-Million Naga City Convention Center Under Probe: PACC Inspection Reveals Vegetation-Overgrown Site And Limited Construction Progress
A government-funded convention center project in Naga City, Camarines Sur, is facing scrutiny after personnel from the Philippine Anti-Corruption Czar (PACC), together with the National Bureau of Investigation (NBI) and the Department of Public Works and Highways (DPWH) Camarines Sur 3rd District Engineering Office, inspected the construction site on November 15, 2026.

Introduction
A government-funded convention center project in Naga City, Camarines Sur, is facing scrutiny after personnel from the Philippine Anti-Corruption Czar (PACC), together with the National Bureau of Investigation (NBI) and the Department of Public Works and Highways (DPWH) Camarines Sur 3rd District Engineering Office, inspected the construction site on November 15, 2026.
The inspection followed complaints from concerned citizens regarding the project's progress and implementation. During the site visit, PACC personnel reportedly found vegetation growing around the steel structures, while only the columns appeared to have been completed despite the millions of pesos allocated for the project.
The development has raised questions about the implementation of the Naga City Convention Center, particularly its construction timeline, the utilization of public funds, and the circumstances behind the project's prolonged delay.
PACC, NBI, And DPWH Conduct Site Inspection Following Public Complaints
On November 15, 2026, representatives from the Philippine Anti-Corruption Czar, accompanied by personnel from the NBI and DPWH Camarines Sur 3rd District Engineering Office, conducted an inspection of the Naga City Convention Center construction site in Barangay Carolina, Naga City.
The inspection was initiated following complaints from concerned citizens who raised questions about the project's progress and the condition of the construction site.
PACC National Chairman Dr. Louie Ceniza expressed disappointment over the site's condition, emphasizing that government-funded infrastructure should translate into facilities that the public can actually use.
During a press conference the following week, Ceniza described the condition of the site, noting that vegetation had grown around the steel structures and that only the columns appeared to have been completed despite the millions of pesos already spent.
His observations brought renewed attention to the project's actual physical accomplishment compared with its approved funding and construction schedule.
₱97.9 Million Contract Awarded To Centerways Construction
Based on project documents, the first phase of the convention center, officially titled "Construction of Multi-Purpose Building Convention Center in Carolina, Naga City," was awarded to Centerways Construction and Development Inc. for ₱97,901,095 under Contract ID No. 23FF0102.
The contract was signed on January 2, 2024, giving the contractor 365 calendar days to complete the project.
On January 3, 2024, the DPWH issued the Notice to Proceed (NTP), formally authorizing the contractor to begin the project. The contractor's representative, Lawrence Lubiano, acknowledged the notice on January 9, 2024.
The contractual period and the reported completion date have become important points in examining the project's implementation. While the contract provided 365 calendar days for completion, former Mayor Nelson Legacion later stated that Phase 1 was completed on April 7, 2025.
The difference between the original contractual period and the reported completion date is among the timeline details that warrant clarification through the project's official records, including any approved time extensions or revisions.
What Happened To The Construction?
Former Naga City Mayor and now Camarines Sur 3rd District Representative Nelson Legacion has denied allegations of corruption and irregularities involving the convention center, maintaining that the project was legitimate and that its implementation was divided into multiple phases.
In his statement, Legacion explained that the first phase, allocated approximately ₱100 million, covered excavation, installation of precast concrete piles, and construction of footings and steel-reinforced columns.
According to him, construction began on January 9, 2024, and Phase 1 was completed on April 7, 2025.
The second phase was allocated another ₱100 million in 2026 under Sub-Allotment No. SR2026-06-017005, dated June 22, 2026.
However, Legacion attributed the delay in the implementation of Phase 2 to an alleged geotagging error by the DPWH.
He explained that the project location was incorrectly recorded as San Jose, Pili, Camarines Sur, instead of its actual location in Barangay Carolina, Naga City.
According to Legacion, the discrepancy affected the processing and implementation of the succeeding construction phase.
He maintained that the error was not attributable to him and referred the public to a project brief submitted to the DPWH Secretary in April 2026, together with supporting documents. He also said he was coordinating with the agency to resolve the issue and resume construction.
Legacion further denied allegations of corruption or irregularities, emphasizing that the project was a legitimate development initiative intended to benefit Naga City.
Mayor Leni Robredo Clarifies Her Administration's Involvement
Meanwhile, Naga City Mayor Leni Robredo clarified that the convention center project currently under PACC investigation was not initiated by her administration.
Robredo pointed out that she was not yet serving as mayor when the construction began in January 2024.
Her clarification distinguishes the project's original implementation from the current administration's responsibilities and underscores the importance of establishing accountability based on the specific period and government officials involved.
The project began under the previous city administration, while the reported inspection and investigation are taking place under the current administration.
Why The Project's Delay Matters
The Naga City Convention Center was envisioned as a major public facility capable of accommodating approximately 5,000 people. Once completed, it is expected to support conventions, exhibitions, conferences, and other large-scale gatherings, contributing to the city's economic and tourism development.
However, a project of this scale requires more than funding allocation and initial structural construction.
From an engineering and project management perspective, construction must follow an approved schedule, with proper coordination between the implementing agency, contractor, and other concerned stakeholders.
Delays in succeeding phases can affect the continuity of construction, expose partially completed structures to environmental conditions, and postpone the intended public use of the facility.
The reported condition of the site also highlights the importance of regular project monitoring, physical accomplishment validation, and proper documentation of construction activities.
For publicly funded projects, the actual work completed must be consistent with approved plans, contract provisions, and reported accomplishments.
Transparency and Accountability Beyond Project Allocations
The PACC-led inspection has brought the Naga City Convention Center into the broader discussion on transparency and accountability in government infrastructure spending.
While Legacion has denied allegations of irregularities and attributed the delay to a geotagging issue, the concerns raised by citizens and the observations made during the inspection emphasize the need for a clearer accounting of the project's implementation.
Several matters deserve further clarification, including the actual physical accomplishment of Phase 1, the reported completion date in relation to the original contractual period, the status of the second-phase allocation, and the steps being taken to resume construction.
Ultimately, the public deserves more than explanations regarding why a project has been delayed. It deserves accessible records, verifiable construction progress, and a clear timeline for completion.
A nearly ₱100-million first-phase contract should result in measurable infrastructure progress. Public funds must translate into structures that are properly built, completed, and made available for the benefit of the people.
References
Philippine Daily Inquirer. Civil society watchdog probes stalled Naga City convention center.
https://newsinfo.inquirer.net/2344822/civil-society-watchdog-probes-stalled-naga-city-convention-center
Politiko Bicol. Legacion denies anomalies in Naga convention center project. November 18, 2026.
https://bicol.politiko.com.ph/2026/11/18/legacion-denies-anomalies-in-naga-convention-center-project/headlines/
Project documents under Contract ID No. 23FF0102, as described in the investigation report.
Statement of former Naga City Mayor and Camarines Sur 3rd District Representative Nelson Legacion concerning the project's implementation and funding.